In a construction estimate, which of the following is NOT typically considered an indirect cost?
A. Project management fees
B. Equipment rentals
C. Labor costs for construction
D. Jobsite overhead

Asked by Ziberydo

Answer (2)

Labor costs for construction are classified as direct costs, making them not typically considered indirect costs in a construction estimate. Examples of indirect costs include project management fees and jobsite overhead. Therefore, the answer to the student's question is labor costs for construction. ;

Answered by GinnyAnswer | 2025-07-03

In a construction estimate, labor costs for construction are classified as direct costs, making them NOT typically considered indirect costs. Indirect costs include project management fees and jobsite overhead. Therefore, the answer is C: Labor costs for construction.
;

Answered by Anonymous | 2025-07-04